The types of shutdowns
used in a plant unit are:
- Scheduled shutdown
- Maintenance shutdown
- Emergency shutdown
- Trips
- Shutdown
to a standby condition.
Scheduled shutdown
A scheduled shutdown is initiated by the
operator during normal operation of the unit when:
- Maintenance
is required or feed supply is low or exhausted.
- The
shutdown procedure will depend on the type of equipment and the process
chemistry.
Some steps taken in a unit shutdown may
include:
- shutting
off the feeds to stop processes and heat generation particularly if
processes are exothermic (produce heat)
- recirculating
feeds from supply tanks so they do not enter the unit
- shutting
off heating or cooling to the unit or feed preheat system
- shutting
off mixing and other mechanical operations
- cooling
and flushing materials from the unit
Maintenance shutdown
When maintenance to the unit equipment is
required, the equipment may need to be entered so that work can take place. The
shutdown should be a scheduled or planned shutdown as per Standard
Operating Procedures where equipment is:
- isolated
(process, mechanical and electrical)
- cooled and depressurised
- purged and gas freed
- cleaned
- gas tested on a continuous basis prior to and during entry.
A planned unit shutdown will prevent:
- plugging of lines or equipment
- possible damage to equipment
- possible injury.
To prepare the unit for shutdown, the unit may
need to be:
- thoroughly
drained and pumped out to remove chemical liquids
- purged
with steam or inert gas to remove vapours
- solvent
washed to remove deposits that build up on the equipment's internal
surfaces
- flooded
with water or a solvent to remove any remaining chemicals
- any
chemicals trapped in the unit must be flushed out.
- isolated
to prevent the entry of hazardous chemicals
- drained
- steam
cleaned to remove remaining deposits.
During decontamination, regular sampling of the
atmosphere inside a unit vessel is required to ensure toxic or explosive
atmospheres do not build up inside the unit that could be a hazard to equipment
or personnel.
Gas testing must be carried out before anyone enters the vessel to ensure the atmosphere is not toxic, explosive or oxygen deficient.
Emergency shutdown
An emergency shutdown is initiated in the event of a fire, major spill, instrument failure, power failure, or total loss of control of chemical or physical processes.
Gas testing must be carried out before anyone enters the vessel to ensure the atmosphere is not toxic, explosive or oxygen deficient.
Emergency shutdown
An emergency shutdown is initiated in the event of a fire, major spill, instrument failure, power failure, or total loss of control of chemical or physical processes.
Emergency shutdown procedures must be followed
during a shutdown sequence.
Trips
Shutdown of a unit can be initiated by the automatic shutdown system. The systems may be shut down automatically because of temperatures, fluid levels, pressures or flows that are above or below trip points.
Typical shutdowns initiated by trips may include:
Trips
Shutdown of a unit can be initiated by the automatic shutdown system. The systems may be shut down automatically because of temperatures, fluid levels, pressures or flows that are above or below trip points.
Typical shutdowns initiated by trips may include:
- low liquid level in a vessel
- high liquid level in a storage
tank
- high viscosity causing
increased load on pumping or mixing equipment
- mixer failure
- pressure to high
- temperature to high
- low feed flows.
Shutting down to a standby condition
When a unit
is to be shut down for a short period of time for maintenance on auxiliary
equipment, the unit is shut down to a standby condition. A standby shutdown
allows a quick startup of the unit after maintenance is completed in order to
minimise lost production time and offspec material.Standard Operating
Procedures must be referred to when shutting down each type of unit to a
standby condition.
A typical standby condition may include:
- recirculating
material upstream and downstream
- reduced
heating or cooling (sufficient to maintain a safe process condition)
- slow-rolling compressors
- venting process gases to flare
- diverting process streams to temporary storage.
![]() |
Process Groups and knowledge Areas ( Planning, Executing, monitoring/controlling and closing). Methods Engineering: 5S, Lean, TPM, Reliability, Availability, Maintainability and Safety (RAMS), FMEAC, KPI'S). Reliability Engineering.
Communication for shutdown
Communication for shutdown
At the completion of this topic you
must be able to give advanced warning of shutdown where possible.Where a
shutdown will affect upstream or downstream process units, advanced warning
must be given to the appropriate personnel to allow them to prepare for, and
react to, the changing conditions. Appropriate personnel would generally include
suppliers of utilities and feedstocks, and the downstream units that receive
the various output streams. Sufficient warning time needs to be given to allow
these other areas to be ready for the shutdown, and to have alternative
disposal or storage ready when needed.
Advanced warning of shutdowns must be communicated. In the case of emergency shutdowns or a process trip, there is not always time to give advanced warnings, but communication must be made with unit suppliers and customers as soon as possible after the trip or emergency shutdown to minimise the adverse effects of the shutdown.
Equipment changeover
Equipment items such as heat exchangers, pumps and filters are often installed in parallel where one equipment item is on duty while the other is on standby – ready to be quickly brought online when the duty equipment requires servicing.
Filters are changed over when the differential pressure across the filter reaches a certain preset high level.
Heat exchangers can be changed over if one heat exchanger is detected as having:
Advanced warning of shutdowns must be communicated. In the case of emergency shutdowns or a process trip, there is not always time to give advanced warnings, but communication must be made with unit suppliers and customers as soon as possible after the trip or emergency shutdown to minimise the adverse effects of the shutdown.
Equipment changeover
Equipment items such as heat exchangers, pumps and filters are often installed in parallel where one equipment item is on duty while the other is on standby – ready to be quickly brought online when the duty equipment requires servicing.
Filters are changed over when the differential pressure across the filter reaches a certain preset high level.
Heat exchangers can be changed over if one heat exchanger is detected as having:
- leaking
tubes causing contamination of a process stream
- fouled tubes.
- Pumps and compressors can be changed over after a preset time period to even out the wear between the two pumps, or if one fails when in service.
Prepare for re-startup
Resetting trips and alarms
After a shutdown, all trips and alarms must be reset in preparation for startup.
Resetting trips and alarms
After a shutdown, all trips and alarms must be reset in preparation for startup.
If the unit is shut down due to a
trip, the cause of the trip must be investigated and any fault rectified before
the trip can be reset for startup.
Trips that are disabled as part of a normal startup procedure must be reactivated after startup as stated in the Standard Operating Procedures.
Before alarms or trips are reset check the cause of the alarm or trip
Before startup, checks are required to ensure all equipment, including equipment not worked on during maintenance, is in a safe and operational condition.
Pre-startup checks will ensure that:
Trips that are disabled as part of a normal startup procedure must be reactivated after startup as stated in the Standard Operating Procedures.
Before alarms or trips are reset check the cause of the alarm or trip
Before startup, checks are required to ensure all equipment, including equipment not worked on during maintenance, is in a safe and operational condition.
Pre-startup checks will ensure that:
- all flanges, valves and instruments are connected
- all
blinds and spades are removed
- all lines are connected
- valves
are lined up and set to the pre-startup position
- all equipment is in a safe operational condition
- levels are correct in vessels
- all
utilities are available and lined up
- all
vents and drains are closed
- all instruments are commissioned.
The various types of units used in
the chemical, hydrocarbons and oil refining industries have differences which
will affect operations. For this reason it's very important to know what are
the functions, responsibilities inside each department in the plants.
Additionally inside each shutdown type we should apply the best global
standards practices as engineering methods ,as well
as engineering reliability. Most of all let's keep in mind
first personal security then asset integrity.
Aucun commentaire:
Enregistrer un commentaire